HVAC SYSTEM (HEATER, VENTILATOR AND A/C) > Blower Resistor (Manual A/C Model)
INSPECTION
1. Check the resistance between resistor terminals.
Preparation tool:
Circuit tester
Terminal No. | Standard | Connection diagram |
4 — 3 | Approx. 0.43 ? |
4 — 2
Approx. 1.03 ?
4 — 1
Approx. 3 ?
2. Replace the resistor if the inspection result is not within the standard.
Wiring diagram
POWER ASSISTED SYSTEM (POWER STEERING) (DIAGNOSTICS) > Control Module I/O SignalWIRING DIAGRAM(1)Battery(5)Engine control module (ECM)(9)Torque sensor (main & sub)(2)Ignition switch(6)Power steering control module(10)CAN communication(3)STEERING warning light (combination meter)(7)Motor(11)VD ...
Inspection
VEHICLE DYNAMICS CONTROL (VDC) > Yaw Rate and G SensorINSPECTION1. YAW RATE & LONGITUDINAL G AND LATERAL G SENSOR SIGNALSTEPCHECKYESNO1.CHECK YAW RATE & G SENSOR.1) Check the installation condition of the VDC control module & hydraulic control module (VDCCM&H/U).2) Using the Subar ...
Removal
EXTERIOR/INTERIOR TRIM > Roof TrimREMOVAL1. CROSSTREK MODELCAUTION:• Before handling the airbag system components, refer to “CAUTION” of “General Description” in “AIRBAG SYSTEM”. General Description > CAUTION">• Airbag system satellite s ...